Mode of Payment 
      PAYMENT SCHEDULE Amount

Residential flats

Instalments Percentage

Initial deposit (Booking)

Rs. 2,00000 /-

1st Instalments

Balance of 20% within 15days

From the date of booking &

Execution of agreement

Rs………………………..

2nd Instalments

Balance of 15% on completion

Of foundation/plinth

Rs………………………..

3rd instalments

Balance of 10% on completion

Of still floor roof slab

Rs………………………..

4th Instalments

Balance 10% on completion

Of 1st floor roof slab

Rs………………………..

5th Instalments

Balance 10% on completion

Of bricks work (Respectively)

Rs………………………..

6th Instalments

Balance 8% on completion

Of 2nd floor roof slab

Rs………………………..

7th Instalments

Balance 8% on completion

Of 3rd floor roof slab

Rs………………………..

8th Instalments

Balance 8% on completion

Of 4th floor roof slab

Rs………………………..

9th Instalments

Balance 6% on completion

Of plastering/Flooring

Rs………………………..

Last Instalments

Balance 5% having

Over possession

Rs………………………..
TOTAL Rs………………………..